Obstacle clearance project: Old bridge demolition project in the extension project section of Line 21

2026-01-08
1 views

Obstacle Clearance: Extension Project of Line 21 - Old Bridge Demolition in the Section


The scope of this project includes the demolition of old bridges ranging from the Shimatai River Bridge on Chuan Nan Feng Highway to the Dongfeng River Bridge on the same road. Within this section, three bridges and their old piles will be removed sequentially from north to south: Shimatai River Bridge, Shuidonggang Bridge, and Dongfeng River Bridge.

The current condition of the Shimatai River Bridge is a simply supported hollow slab girder with a span of (20m) and a deck width of 40m. The reconstruction plan involves demolition and rebuilding, including the removal of old piles (the old piles are 600mm diameter bored cast-in-place piles, 33m in length, with an estimated 24 piles to be removed). The substructure consists of bored cast-in-place piles, tie beams, columns, and caps. The superstructure includes: railings, asphalt layer, steel-reinforced concrete pavement layer, and precast concrete hollow slabs.

The current status of the Shuidonggang Bridge is a simply supported hollow slab girder with spans of (8m+8m+8m) and a deck width of 40m. The reconstruction plan involves demolition and rebuilding, including the removal of old piles (the old piles are 800mm diameter bored cast-in-place piles, 41m in length, with an estimated 28 piles to be removed). The substructure consists of bored cast-in-place piles, tie beams, columns, and caps. The superstructure includes: railings, asphalt layer, steel-reinforced concrete pavement layer, and precast concrete hollow slabs.

The current status of the Dongfeng River Bridge is a simply supported hollow slab girder with spans of (8m+8m+8m) and a deck width of 38m. The reconstruction plan involves demolition and rebuilding, including the removal of old piles (the old piles are 800mm diameter bored cast-in-place piles, 41m in length, with an estimated 36 piles to be removed). The substructure consists of bored cast-in-place piles, tie beams, columns, and caps. The superstructure includes: railings, asphalt layer, steel-reinforced concrete pavement layer, and precast concrete hollow slabs.



 


 


 


 

Project Challenges:


  1. Since Chuan Nan Feng Highway is a major traffic artery, road closure is not possible, resulting in limited construction space and restrictions on machinery use.


  2. The lifting operations involved in the project (such as component hoisting and equipment transfer) need to frequently cross pedestrian and vehicle lanes on the highway. The openness and mobility of the working environment pose significant safety risks, thus requiring dedicated personnel for full-time supervision.


  3. Many of the existing old piles in the project area have a "big belly" problem (i.e., the local outer diameter of the pile far exceeds design standards or normal dimensions), which poses numerous challenges for handling these old piles (such as removal, cutting, repair, etc.).