"Two walls in one" deep foundation pit project: China Shipping Building

2026-01-08
1 views

“Two-Walls-in-One” Deep Excavation Project: China Shipping Tower

The foundation pit covers an area of 7,430 m² with a perimeter of 346 m and is classified as Grade I in terms of safety level. The retaining structure employs a diaphragm wall system using the “two-walls-in-one” approach, with a wall thickness of 800 mm and a depth of approximately 42 m. The excavation depth is 18.30 m, supported internally by four levels of reinforced concrete bracing. Prior to construction, an old dry dock was found on the central-western side of the site, extending about 50 m into the plot. Obstruction removal—including prefabricated dock structures, cast-in-place surface slabs, and existing piles—was required before construction commenced.

Key Challenges Addressed:

1. Significant deformation and displacement of the excavation may occur during digging, posing substantial impacts on the surrounding environment;

2. The confined site area demands high standards for civilized construction practices, significantly increasing the complexity of construction planning and coordination;

3. Obstruction clearance at the location of the old dry dock on the western side is highly challenging, involving extensive work volume and prolonged duration;

4. The project comprises numerous sub-works with intensive cross-operation activities, resulting in high organizational complexity and elevated safety risks.