Dual-liquid rapid setting micro-disturbance mixing pile patent application project: No. 12 Bridge Project at Jinyuan 5th Road Station on the Jiamin Line in Shanghai

2026-01-08
1 views

Patented Dual-Liquid Rapid-Setting Low-Disturbance Mixing Pile Application Project: Jiading–Minhang Line, Jinyuan 5th Road Station, Bridge No. 12 Project, Shanghai

Some of the piles of Bridge No. 12 are located within the shield tunneling alignment of the Jiading–Minhang Line, obstructing shield machine passage and requiring removal. Since the closest distance between these bridge piles and the operational Shanghai Metro Line 14 is only 3.7 m, construction disturbances during pile extraction could adversely affect the metro tunnel. Therefore, a row of isolation piles was installed between the bridge piles and Metro Line 14. After coordination with Shentong Metro Group and Shensui Design Institute, the isolation piles were constructed using the patented dual-liquid rapid-setting low-disturbance mixing pile technology, which offers minimal ground disturbance and rapid setting characteristics.

Project Challenges:

1. Overhead high-voltage power lines exist above Bridge No. 12, limiting the maximum height of the piling rig to 21 m. Given that the dual-liquid rapid-setting low-disturbance mixing piles are 31 m long, the drill rods must be installed in segments.

2. Continuous construction of the entire row of mixing piles would cause significant soil liquefaction. However, the dual-liquid rapid-setting piles achieve the strength of the in-situ soil within 4 hours. Therefore, a “drill one, skip three” sequence was adopted to leverage the rapid-setting and early-strength properties of the piles, ensuring that the time interval between adjacent panel constructions exceeds 4 hours for proper overlap.

3. Full coverage of steel road plates (trackway mats) was laid along the piling rig’s travel path to distribute construction loads and minimize ground impact caused by equipment self-weight.