Caisson construction project: Baosteel Bar Steel Plant cyclone tank project

2026-01-08
1 views
Case Study Template

1. Project Name: Caisson Construction Project – Baosteel Bar Mill Cyclone Pit Project

2. Construction Photos (3–5 images):

Panoramic Construction View

Construction in Progress


 

Schematic Design Plan

3. Project Overview:

This project is located within the Baosteel Bar Mill plant in Shanghai. The cyclone pit is situated east of the newly constructed No. 2 roller bay, adjacent to the main workshop and new column foundations. The cyclone pit features a deep circular reinforced concrete underground structure, consisting of inner and outer shafts. The ground level is at -0.5 m, the top of the base slab is at -20.625 m, and the top of the caisson wall is at +0.500 m. The outer shaft of the cyclone pit was constructed using the jacked caisson method, with a wall thickness of 1 m, an outer diameter of 16 m, an inner diameter of 14 m, and a total caisson height of 25.6 m. The caisson is a circular reinforced concrete structure with concrete strength grade C30 and waterproofing grade S8. The caisson was cast in three sections and sunk in three stages, with segment heights of 8.0 m, 8.5 m, and 9.1 m respectively, achieving a total sinking depth of 25.1 m.



  1. Project Challenges:


  1. The outer wall of the cyclone pit is only 3.9 m from the N36 column foundation of the main workshop and 4.5 m from the N35 column foundation—very close to existing structures. To address the limitations of caisson construction in such a sensitive environment, theoretical analysis was used to determine the optimal soil plug thickness, jacking reaction system configuration, and applied downward force. By actively applying controlled downward pressure, adverse soil resistance effects were mitigated, ensuring sufficient sinking coefficient while minimizing disturbance to the surrounding environment. This approach transformed passive sinking into active, controlled sinking, improving construction efficiency and reducing environmental impact.


  2. Tilt is prone to occur during initial sinking. To prevent this, the removal sequence of the bedding layer was strictly controlled. The plain concrete bedding was broken symmetrically in zones, following an inside-to-outside removal sequence. Additionally, an appropriate soil plug was retained inside the caisson to regulate sinking speed.


  3. During sinking, excavation inside the caisson must be symmetrical and uniform. Enhanced monitoring was implemented throughout, adhering to the principle of “frequent measurement and prompt correction” to ensure smooth and stable sinking.