Rectangular pipe jacking project: Fuzhou to Changle Airport intercity railway project Fuzhou Railway Station transfer channel pipe curtain project
Rectangular Pipe Jacking Project: Tube Roof and Pipe Jacking Works for the Transfer Passage at Fuzhou Railway Station, Fuzhou–Changle Airport Intercity Railway Project
The tube roof and pipe jacking works for the transfer passage at Fuzhou Railway Station involve installing an upper and lower row of Φ800 mm tube roof pipes above and below the jacking corridor. After completion of the tube roof, rectangular pipe jacking excavation proceeds. The external dimensions of the jacked section are 10.8 m × 5.9 m, with a clear internal dimension of 9.5 m × 4.6 m. The passage length is 109.5 m, with a cover depth of 4.5 m. Construction utilizes a 10-cutterhead earth pressure balance rectangular pipe jacking machine.
Project Challenges:
1. Extremely large cross-section pipe jacking presents high construction difficulty;
2. Long jacking distance through mixed ground conditions requires precise alignment and attitude control;
3. The jacking route closely overpasses the operational Metro Line 1 and underpasses multiple critical municipal utility lines, demanding strict control of ground settlement;