Subway station enclosure construction project: Fuzhou Binhai Express (Line F1) South Park Station
Metro Station Retaining Structure Construction Project: Nan Park Station on Fuzhou Coastal Express Line (F1 Line)
Nan Park Station has a total clear length of 174.3 m, with a curved platform width of 14 m and a standard section clear width of 39 m. The station features four entrances/exits and two sets of ventilation shafts. The average overburden thickness above the station box is approximately 3.0 m. The standard section of the main station structure is excavated to a depth of about 19.1 m, while the small-mileage end shaft reaches an excavation depth of 20.9 m. The retaining system consists of 1,000 mm thick diaphragm walls, reinforced with triple-axis soil mixing piles along the trench walls, and supported by a three-level concrete bracing system.
Project Challenges:
1. The pile diameter specified in the original design differed significantly from the actual diameter of the piles to be extracted, necessitating replacement of the casing;
2. To ensure construction safety, workers cannot enter the excavation once the grab has reached a depth of 30 meters; therefore, the grab bucket was reinforced to enable remote extraction of the piles;
3. To guarantee safe pile removal, double-lashing was implemented when extracting piles from the casing;
4. To ensure the quality of bored piles constructed within the river channel, a dual-pump circulation slurry system (using both large and small pumps) was adopted.