Water PC construction method combined steel pipe pile project: Zhanjiang Jingxin Donghai Power Plant Cofferdam Project

2026-01-08
1 views

Underwater PC Method Combined Steel Pipe Pile Project: Zhanjiang Jingxin Donghai Power Plant Cofferdam Project

The Zhanjiang Jingxin Donghai Power Plant’s 2,600 MW “large-replace-small” combined heat and power (CHP) unit project is located in Dongshan Town, Donghai Island, Zhanjiang City—approximately 1.5 km northeast of Hongxing Reservoir, within the subtidal coastal zone. The steel cofferdam piles are 30–34 meters long, constructed using Ø820 interlocking steel pipes, installed via marine piling operations. Half of the cofferdam lies underwater, while the other half crosses the seawall and is founded on tidal flat soil.

Project Challenges:

1. With pile lengths of 30 m, high verticality control is required during driving; the interlocking mechanism between pipe piles demands extremely high precision;

2. Half of the cofferdam is submerged, and the other half traverses the seawall onto tidal flats, making marine transportation and construction logistics highly challenging;

3. Riprap and wave-dissipating boulders along the shoreline extend 8–9 m deep, directly interfering with cofferdam installation;

4. The tight schedule necessitates simultaneous work across multiple fronts, resulting in multiple closure joints, which imposes even stricter accuracy requirements on steel pipe pile alignment and interlock integrity.