Micro pipe jacking technology: 2nd standard micro pipe jacking project for the new project of Huanyuan South Road (Nanliu Highway ~ Dachuan Highway)
Micro Pipe Jacking Technology: Micro Jacking Works for Package 2 of the New Construction Project on Huanyuan South Road (Nanliu Highway to Dachuan Highway)
Project Overview:
This project involved micro jacking of a DN300 sewage pipe over a length of 61 meters, with a gradient of -0.2%, and cover depths ranging from a minimum of 7.241 m to a maximum of 7.351 m. The entire construction duration was 24 days. The working shafts were constructed using a dual-head hydraulic vibratory hammer; from installation of the hammer to driving the steel casing, the process was completed within 12 hours. The jacking operation was carried out in three phases: Phase 1 (guidance pilot pipe installation) took 12 hours; Phase 2 (slurry discharge pipe installation) took 12 hours; and Phase 3 (pipe segment jacking) took 11 hours.
Project Challenges:
The site had a complex working area with overlapping construction activities, impacting the schedule;
High-voltage power lines were present overhead, making equipment lifting difficult;
The geological conditions featured Layer 3 interbedded strata, containing significant confined water and sand;
The alignment had to cross a 24-meter-wide boundary river, with underground obstructions located near the embankment.
Technical Advantages:
No disruption to existing underground utilities, road traffic, waterways, or surface structures. The construction is noise-free, environmentally clean, and requires minimal excavation—only a 3-meter-wide road is needed. The smallest working shaft diameter is 2.5 meters, and the smallest reception shaft diameter is 1.5 meters.
Cost-effective and suitable for lifting operations in confined spaces. The equipment is compact yet powerful, enabling fast jacking speeds and excellent waterproofing performance, with a total horizontal deviation of only 30 mm throughout the jacking process.
High-precision visualized control ensures real-time monitoring and correction of deviations, keeping the entire process under strict control, resulting in high efficiency and short construction duration.
Applicable in various ground conditions including soft soil, clay, sandy soil, gravelly soil, hard soil, and backfilled ground. Particularly suitable for installing micro pipelines beneath complex urban infrastructure where open-cut excavation is not feasible, ensuring no damage to surface buildings.